Arundel Tidal Defences Scheme Update – 29 May 2020

Latest Update from the Environment Agency: River wall improvement works Now that the installation of steel sheet piles over the full extent is complete, our priority now is to provide additional stability to the overall construction.  This week, the two large cranes used to install the steel sheet piles were removed from site. These have been replaced with … Continue reading Arundel Tidal Defences Scheme Update – 29 May 2020