Arundel Tidal Defences Scheme Update – 10 July 2020
Latest Update from the Environment Agency: River wall improvement works All ground anchors have now been installed into the new river wall. Works will continue over the next week to apply tension to the ground anchors to ensure the new structure achieves the appropriate design parameters for overall strength and stability. Backfilling up to design … Continue reading Arundel Tidal Defences Scheme Update – 10 July 2020